|
The Second
Supply Project
Lakehaven Utility District will be
introducing a new source of drinking water to customers. Beginning
November 14, 2005, Second Supply Project (SSP) water, obtained from the
protected Green River watershed in the foothills of the Cascade
Mountains, will be introduced into the water distribution system. Water
from the Green River watershed and Howard Hanson Reservoir has been used
to serve the City of Tacoma since 1913. With the Second Supply Project,
a new pipeline, running over thirty miles from the existing diversion
near the Howard Hanson Reservoir through the Federal Way area to Tacoma,
is being placed in service to provide additional water to the City of
Tacoma, City of Kent, Covington Water District, and the Lakehaven
Utility District service areas. When in full operation, Lakehaven will
be able to utilize over 12 million gallons of water per day from the new
source. The water from the Second Supply Project will allow the District
to decrease demand on the aquifers that provide the current supply and
handle the increase in customer demand projected for the area.
While the water from Tacoma’s Green River
watershed meets all state and federal water quality standards, certain
physical and chemical differences between this surface water source and
Lakehaven’s current groundwater supply may be noticeable to customers.
Lakehaven’s existing groundwater sources are treated with chlorine, but
not fluoride. Tacoma treats its water with fluoride and a higher
concentration of chlorine. The additional source of water from Tacoma
will blend in the distribution system with the District’s groundwater
resulting in changes in these water quality characteristics. While other
differences may be apparent to some customers, the additional source is
needed to help ease demand on local groundwater resources.
Lakehaven customers will be receiving a
special notice in the mail informing them that the District will be
adding this additional drinking water source in the coming weeks.
Lakehaven Utility District customers may refer to the
Water Quality
page of the District’s web site for additional information on Tacoma’s
water quality and see below for a brief description on the status of the
entire Second Supply Project.
The Second Supply Project Description
The Second Supply Project is a regional
project to provide up to 65 million gallons of water per day from the
Green River to the City of Tacoma, City of Kent, Covington Water
District, and Lakehaven Utility District.
The Project includes:
- Howard Hanson Dam Additional Storage
Project
- Tacoma’s Headworks Diversion
Improvements
- The Second Supply Pipeline
- Water Treatment Facilities
- Off-Site Wetlands Enhancement
Project
Status, as of October 2005:
Howard Hanson Dam Additional Storage
Project:
Howard Hanson Dam is an existing surface
water impoundment dam built in 1962 on the Green River system to protect
the Auburn/Kent valley from flooding. While it’s primary function is
flood control, it will also be used to store additional water for
municipal and environmental needs. Currently, installation of the
cofferdam that is needed for construction of the fish trap-and-haul
facilities is underway. This work is proceeding under Army Corps of
Engineers direction. The cofferdam placement and related rock excavation
work should be done by approximately April 2006. Some of the associated
fish and wildlife habitat mitigation projects were installed in 2005 by
Tacoma Water and the Corps and more will be installed in 2006. It is
expected that the Corps will select a contractor for design/build of the
new fish facilities by the end of 2006. All storage project construction
work should be fully completed by 2008 or 2009; however, some water
storage for municipal purposes and stream flow enhancement may be
available for the 2006 summer season.
Tacoma’s Headworks Diversion
Improvements:
All work (raise diversion dam, new river
intake, new fish handling facilities, intake building, supply pipeline
and area restoration) is completed except for a few minor punch-list
items that the contractor is finishing.
The Second Supply Pipeline:
The 34 mile pipeline was built in 5
sections beginning in 1999 and is currently complete and available for
service. The first section, called the NE Tacoma/Federal Way Section,
was the first piece initially funded by Lakehaven and completed in 2000.
The Kent/Covington Section was then placed in service in August 2002.
The Easterly Middle Section was completed in 2004. The Headworks Section
and the Westerly Middle Section were completed in September, 2005.
Startup procedures, including disinfection and testing, were completed
in October 2005.
Water Treatment Facilities:
A contract was let last summer for
construction of the new chemical feed building, which includes
chlorination, fluoridation and pH adjustment for corrosion control. The
project is essentially complete and is going through final punch-list
items. The testing and Startup of the facility were completed in August
of 2005 and it is now treating water at the Headworks. Design is well
along for a new Headworks operations building and construction bids
should be received early next year, with completion of the facility
scheduled for spring of 2007. The next phase of water treatment will
involve ozonation and those facilities should also be constructed by
spring 2007.
Off-Site Wetlands Enhancement Project:
The King County property to be restored
is located immediately downstream of where SR18 crosses the Green River.
King County constructed a fish refuge channel last year on the
downstream portion of the site and it will eventually be connected to
the Green River at Auburn Narrows, probably in 2006 or 2007. The Second
Supply Project has contracted for wetlands restoration on the upstream
portion of the site. More than half of the restoration work was
completed by the Fall of 2004 when it was suspended because of muddy
conditions caused by rain and high surface water levels. Restoration
work was back in progress last summer and all work should be completed
by the end of 2005 or the spring of 2006. |