|
Redondo Outfall
Project
TENTATIVE SCHEDULE as of
10-23-08 (subject to change on a daily basis)
-
A temporary outfall
pipe was installed and was temporarily visible on the beach. - COMPLETE
-
Next, the first outfall
segment (approximately 700 feet long) was installed and is active. -
COMPLETE
-
Next, an offshore
anchor block was installed and anchored in place with 4 piles. -
COMPLETE
-
Next, the temporary
pipe was reused and fused together with another segment of pipe to form
the final 1,700 long segment. - COMPLETE
-
Next, the final segment
was sunk in the Sound with a small gap between the first segment and the
last segment. - COMPLETE
-
Finally, the small gap
will be filled by a small pipe segment that will complete the
approximately 2,400 feet long outfall
Major Remaining Activities
-
Install final small
piece of pipe between the first 700 feet (already active) segment and
the final 1,700 feet segment that was installed at the end of September
– Monday October 27 through Wednesday October 29.
PRESS RELEASE:
July 29, 2008
Andy Wilt, Project Manager
LAKEHAVEN SINKING $4.8 MILLION INTO PUGET
SOUND PROJECT
In an effort to enhance water quality protection
measures in the Redondo Beach and surrounding marine environment, the
Lakehaven Utility District will sink $4.8 million into the upgrade of the
Redondo Wastewater Treatment Plant outfall line. The outfall discharges
treated wastewater effluent into the Puget Sound.
Construction began in July on a project to
replace the existing Redondo Wastewater Treatment Plant marine outfall pipe,
located near the southern end of the boardwalk along Redondo Beach Drive.
The original marine outfall was constructed in 1963 and consists of a
30-inch diameter pipe extending approximately 1,030 feet offshore. The
existing outfall line is approximately 123 feet below sea level at its
terminus.
With the existing outfall pipe having reached
the end of its service life, the Lakehaven Utility District Board of
Commissioners approved a project to construct a new outfall. The new line
consisting of a 24-inch diameter, high-density polyethylene (HDPE) pipe
extending approximately 2,420 feet offshore to a terminus depth of
approximately 400 feet below sea level. The HDPE pipe has an expected
service life of over 100 years, and will deliver treated wastewater from the
Redondo Wastewater Treatment Plant nearly a quarter-mile farther than the
terminus of the existing line and beyond the sensitive near-shore
environment.
Extensive planning has been undertaken to
minimize neighborhood and environmental impacts from the construction
activities. One of the mitigation measures implemented by the District is
to schedule construction activities during optimal tidal cycles, while at
the same time minimizing the amount of work taking place at night.
Construction is expected to be complete by early September.The planning,
permitting, design, and bidding costs for the project totaled approximately
$1.8 million. The construction costs, including construction management and
inspection, are expected to run in the neighborhood of three million
dollars. Lakehaven Board President Ron Nowicki believes the money is well
spent. “This project is an investment by our ratepayers in necessary sewer
system infrastructure and is also a significant contribution to the efforts
to maintain the health of the Puget Sound”.





|