Issues to Consider for
Design/Construction of Low Pressure Sewer Systems (Grinder Pumps)
1) Current Method for Gravity Sewer Design/Construction (as
applied to Developers and past ULID's):
- Developer/LUD Design infrastructure in Right-of-Way (and Public
Easements in private property, if necessary) subject to LUD standards
and approval.
- Finish floor elevations are surveyed to determine minimum depth of
gravity system.
- Sewer Stubs are provided to adjacent properties (typically at the
lowest corner of property for gravity stubs).
- Stubs typically extend 10 feet onto private property to terminate
beyond other underground utilities (unless owner denies access).
- Property Owners typically hire a contractor to connect House to the
Stub (Property Owner can do the work on private property, but need an
approved contractor for work in Right-of-Way).
- Contractor/Owner requests Side Sewer Permit.
- Contractor/Owner makes connection and calls LUD for Inspection.
- LUD inspects and approves installation after meeting LUD standards.
- LUD draws and maintains record of As-built Side Sewer on Private
Property.
- Property Owner maintains Side Sewer from House to Property Line.
2) Alternative Methods of Sewer Design/ Construction:
- Is the District going to Own the facilities on Private Property?
- If No
, then the following does
not apply.
If Yes, is the District going to design the Individual Pump Systems?
- If No,
Property Owner provides an Engineering Design approved by
District.
If Yes, LUD needs to prepare individual site designs for each
property.
- Where does Design End?
- If LUD Design Ends at the Pump chamber,
- LUD develops Onsite Piping Plan
- Determine lowest elevation to be serviced
- Determine Owners preferred Pump chamber location.
- Determine Pump Size/Capacity
- Determine Size of Force Main from Pump chamber to edge of
Right-of-Way (or Easement)
- Determine Route of Force Main
- Consider, Location of building or other remote
structures, fences, irrigation system piping,
underground lines (power, gas, water, cable, etc.),
landscaping (special grasses, tree, shrubs, rockeries,
etc), significant obstacles (driveways bulkheads, etc),
and other neighbor or homeowner concerns.
- Specify tracer wire for future locates.
- Determine if Auxiliary Power/Emergency Generator will be
provided.
- If Yes,
- Size Pump chamber/Holding Tank.
- Specify abandonment of Septic Tank (if not used).
- If No,
- Obtain permission to use existing septic system
for emergency overflow.
- If Yes,
- Determine location of drainfield/tank
- Assess condition of drainfield/tank
- Design overflow route to drainfield/tank.
- If No,
- Over size Pump chamber/ Holding Tank.
- Specify abandonment of Septic Tanks (if not
used)
- Property Owner would provide fixture count for pump and pump
chamber sizing.
- Property Owner would be responsible for specifying power
available, 120v, 240v, etc.
- Who is responsible for gravity section from House plumbing to
Pump chamber (LUD or Property Owner)?
- Location of building drain(s) leaving home. [UPC defines]
- Obtain Owner's approval of On-site Piping Plan.
If LUD Design Ends at the Normal Power supply,
- LUD would be responsible for ensuring adequate power supply is
available from the Owner's power service to the home. Commercial
Electrical Standards might apply to LUD.
- LUD develops site electrical plans for contractor
- Need access inside the home.
- Need floor plan of house.
- Determine power available 120v, 240v, etc. (What if
service panel is already overloaded?)
- Determine where pump(s) load center/control panel will be
located
- Determine route from customer's electrical circuit breaker
panel to pump(s) load center/control panel (can it?)
- Determine location of Remote Disconnect at pump(s) location.
- Determine if Auxiliary Power/Emergency Generator is needed (Would
we design? Emergency plug and/or transfer switch?)
- Determine location of residential alarm unit and enunciator.
- Obtain Owner's approval of electrical site plans
Is the District going to administer construction of the Individual Pump
Systems?
- If No,
(same as current method, repeated below)
- Property Owners typically hire a contractor to connect House to
the Stub (Property Owner can do the work on private property, but
needs an approved contractor for work in Right-of-Way).
- Contractor/Owner requests Side Sewer Permit
- Contractor/Owner makes connection and calls LUD for Inspection
- LUD inspects and approves installation after meeting LUD
standards.
- LUD draws and maintains record of As-built Side Sewer on Private
Property.
- Property Owner maintains Side Sewer from House to Property Line
ii) If Yes, Where does Construction End?
- If LUD Construction Ends at the Pump chamber,
- LUD issues Side Sewer Permit
- LUD makes connection from pump chamber to Right-of-Way (or public
easement)
- LUD obtains Temporary Construction Easement or Right of Entry on
each Private Property (Drawing).
- Obtain Pre-Construction Photos of All sites.
- Schedules on-site construction activity with each property owner
- Utilize different construction equipment (small backhoes, Ditch
Witch)
- Site restoration to satisfy Property Owners
- Who connects from House to Pump chamber (need to get into basement
(finished or unfinished) or under house/crawlspace)?
- Who connects from Pump chamber to overflow (if any)?
- LUD inspects and approves installation after meeting LUD
standards.
- LUD draws and maintains record of As-built Side Sewer on Private
Property.
- LUD maintains from Pump chamber to Right of Way (or easement),
Standard Warranty 1 year? (or Longer? see Maintenance for Individual
Pump Systems)
- Property Owner ensures adequate power to pump, the electrical
connection, location of load center/control panel, location of power
disconnect, auxiliary power/emergency generator if desired, and the
location of alarm system and enunciator.
If LUD Construction Ends at the Normal Power Supply?
- LUD makes electrical connections from Pump to house Circuit Breaker
Panel.
- Obtain Right of Entry into home.
- Obtain electrical permits for each home. Commercial Electrical
Standards might apply to LUD.
- Schedules in-house activity with each property owner.
- Utilize different construction techniques/equipment (electricians,
wire/conduit, wallboard work, etc.)
- Site restoration to satisfy Property Owners.
- LUD Maintains electrical system from Circuit Breaker Panel to Pump,
Standard Warranty 1 year? (or Longer? see Maintenance of System)
Is the District going to provide Maintenance for Individual Pump
Systems?
- If No, standard warranty for installations/products is typically
1 year.
- If Yes
,
- Contract for Outside Service?
- Where does maintenance End?
- If maintenance ends at the Pump chamber,
- LUD maintains pump, pump chamber, and Side Sewer (force main
to road or public easement)
- Requires Permanent Access Easement or Right of Entry onto
property
- Responsible for repairs to Pump, Pump Chamber, Side Sewers
(force main), check valves, clogs, odor, etc.
- Responsible for responding to Pump Alarms (real or false)
- What about overflow lines to Septic tank, if any?
- Replacement Cost of all components for life of Home? For
life of equipment? For residency of current occupants?
- Who is responsible for Overflows, cleanup, or property
damage?
- Due to backups?
- Due to blockages?
- Due to power failures?
- Due to Acts or Omissions of Others?
- Property Owner maintains from House to Pump chamber.
- Property Owner pays for Power?
- Property Owner pays additional Cost of Maintenance?
If maintenance ends at the Power Supply,
- LUD maintains wiring in or around home or at Remote
disconnect?
- LUD maintains Auxiliary Power/Emergency Generator (if any)?
- Does Pump system require Separate Power Meter for a
particular Home?
3) Financing:
- Is the District willing to consider installation of Main Line
Facilities in roads and public easements as a "District funded
Project"?
- If No, ULID process, Bond Sales (or other), Assessments
- General Rule of Thumb, if project is less than $1M, other types of
financing may be cheaper.
- Assess all costs to Logical ULID properties
- Likely to be applying assessments to unwilling Property Owners
- May impact ULID Formation
- Board willingness to allow properties to opt out? (Working septic
systems)
- c) If Yes, District Project, Latecomer Fee or Charge in-lieu of
Assessment (w/interest)
- No ULID Formation Process
- Customers pay at time of connection (no public financing; must
arrange own financing)?
- Typically sewer projects have provided stubs to all adjacent
property when installed, to minimize damage to new street pavement
repair, landscaping repair, etc. Pressure sewers are more like water
systems for making additional taps and connection in terms of relative
simplicity. Would District want to provide stubs to non-
participating Property Owners as part of a District Project?
- Some Combination?
- Is the District willing to finance the On-site facilities? (Will
financing have any implications on Ownership?)
- If No, then the following does not apply.
- If Yes, What should the District finance?
- Installation of Entire On-site System?
- Need approved Piping and Electrical Plan and Cost Estimate
prior to Construction Bidding (including Pump Specifications)
- Installation of Pump chamber and Side Sewer (force main) only?
- Need approved Piping Plan and Cost Estimate prior to
Construction Bidding (including Pump Specifications)
- Purchase of Pump and Pump chamber only?
- Need approved Pump Specifications
- What should the District do with Pumps until ready for
installation?
- Store at District Facilities until Property Owner is ready
to install?
- Deliver to Property Owner when received for them to store
until installed?
|
|